Pre-Build Timeline

Oct 21, 2012 Paid $950.00 to Rawson
Modifications on Ben 33 back and forth from salesguy and us
Nov 28, 2012 Tender Preview

Dec 17,  2012 Signed tender and paid $3000.00, CSO assigned
Jan 18, 2013 Color selection appointment email received
Jan 20, 2013 Received Client check plans by mail  
Feb 18, 2013 Color Selection appointment
Feb 21, 2013 After so many changes, Color variations signed and sent back
Feb 26, 2013 Tile Selection Appointment
Mar 11, 2013 Color plans drawn up for submission, CSO changed 
Mar 14, 2013 CSO requests for the proposed pool details
Mar 18, 2013 Color plans signed and sent, more variations on plans. 
Mar 19, 2013 Variations signed and sent
Mar 21, 2013 Amended Color Plans received
Mar 22, 2013 Color plans signed and send
Mar 24, 2013 Discussion with our sales consultant with regard to the pool
Mar 27, 2013 Variation raised for additional piering for the pool which will be done after handover
Apr  9, 2013 CSO received BASIX certificate
Apr 9, 2013 Variation raised for landscaped reduction, signed and send
Apr 10, 2013 Electrical Appointment booked for 17th 