Tuesday, December 10, 2013

Fencing down, painting

The fences have been taken off and we could see our finished house without any obstruction. .

More clearer pics ;)

The painters were also on site to finish alfresco and remaining external painting and stains

Thursday, December 5, 2013

Door furniture

The door furnitures for all rooms have been installed.

I love my main door.it looks so elegant

Walk through 4th Dec, plumbing, electricals, tilers on site

Most of the works have now been completed.. electricals, plumbing and insulation

Painting 23 Nov


Painters are on site today. They are doing a good job. . I must say!
I love Martini.. its going so well with white. I can see myself doing a lot of stuffs on wall, 'cos it will all match Martini..

Friday, November 15, 2013

Painting, electricals

After a long wait painters were back on site and did enough for the electricians to carry our their works.

All our down lights,  staircase lights, security systen and flood lights are in..

Caesarstone, Bathroom vanities, tiles

The bathroom vanities are all in.. and the feature tiles installation is also complete.

Rawson signage


Finally we have a Rawson signage on our block.

Monday, October 28, 2013

Walkthrough - kitchen

Kitchen cabinets have gone in.

Walkthrough - alfresco, porch tiling

We have had to change our selections for the alfresco and porch since the tiles were discontinued. 

Alfresco tiles

Walkthrough - cornices and wet area tiling

We went in for a walk through to have a look at the work completed so far.
The cornices have been installed. The tiling looks great. I am very happy with our selections so far.
Here are pics of our tiles:

Ensuite

Ensuite Tiles and shower niche   

Shared Bathroom - Tiles and shower niche 

 Cabinets - shared bathroom.
Yes, i see broken tiles ;) it will be fixed. The cabinets were supposed to go in first and then the tilings, but the kitchen guys delayed it and hence the mess
 
 

Powder Room with shower - they forgot to install the feature tiles in shower niche. I notified Tile Direct and they will fix it. 

 

Friday, October 25, 2013

Garage door

The contemporary garage door is in. We opted for the same colorbond color of the weatherboards. I think its looks really good. Can't wait for the Charcoal driveway so that it will all look perfect.

Sunday, October 20, 2013

Lockup, Stairs complete, Rainwater tank installed

The doors have been installed. Eventhough we didn't get the door we ordered,  still okay with the alternate one. It will atleast match the stairs with timber and steel looks ;). The staircase looks complete except for staining.

I've been advised that kitchen is delayed by a week. Hopefully it will all be installed this week.

Sunday, October 13, 2013

Lower bricks cleaned, Staircase installed & Temporary lockup

We had the staircase installed this week. Few doors have been installed.
More pics of the house.

Lower bricks cleaned

Staircase installed 
Master Bedroom - We moved it to the front of the house. I didnt expect the windows to be this big. Happy with it.
Upstairs Lounge - Our TV niche 
 

Monday, October 7, 2013

Electricals, Insulation

Last week we had the electrical rough ins.
The timber feature went in and the insulations works were started. Gyprock is delivered on site and they should be on it this week.
Lockout for Friday. . Yeah.. getting closer and closer. ..

Thursday, September 26, 2013

Scaffolding down.. :)

Scaffolding is taken down this week. Roof tiles were installed for alfresco and garage. As per the SS, electrical rough ins also starts this week. Rawson' s inspectors are also scheduled for this week.

Our private inspector will be going to site next week

Brick cleaning, Painting

There was not much work in site last week.
Half of the bricks were cleaned and painters were in to paint the weather boards,  eaves and downpipes. Its looking good

Saturday, September 14, 2013

Eaves and Weatherboards are in

This week we had the carpenters come back on site to fix few windows. The roof rails are taken down. The eaves and weather boards are in. The cedar screens are fixed on one side. Brickies also should be back to fit window sils.

Next week is going to be a quiet one with the brick cleaners scheduled on Thursday and painters on Friday for painting weather boards. 

Sunday, September 8, 2013

ROOF

We have a roof (happy dance). Garage and alfresco roofs are yet to be laid.

Bricking complete, Gutter and fascia installed

Here are some pictures. So officially bricking is completed. Gutter and fascia has gone in.

Roof tiles are delivered on site.

Saturday, August 24, 2013

Upper storey bricking

Brickies were on site this week and they are close to completing the upper storey bricking. Its expected to be completed by Monday.

Sunday, August 18, 2013

Scaffolding

Scaffolding went up last week. Ground floor bricking is close to completion. The pillars for alfresco is complete

Saturday, August 10, 2013

Bricking

Bricking started on Friday and our house is slowly starting to take its shape. We drove to our site over  the weekend and saw brickies at work.
Happy happy so far.
Also had a chat with my SS and he reckons this should be complete in two weeks, provided it doesn't rain.

Garage 

Kitchen, family

Alfresco  


Wednesday, August 7, 2013

Bricks Delivered, frames completed

Bricks got delivered today and brickies will start either tomorrow or the day after.

The garage and alfresco frames are put up and officially its completed. The laundry doors and glass splashback in kitchen is also fixed.

I will update pictures over  the weekend

Friday, August 2, 2013

Second storey frames

Second storey frames started yesterday (2 Aug 2013)
SS told that it should be completed by Monday/Tuesday and bricks arrive on Tues/Wed.
Btw, we had to change our bricks selection again because Boral was able to find a stock of Blackheath for us.

Tuesday, July 30, 2013

Frames

The frames are up. Its exciting to see the house taking its shape slowly. The windows and stacker doors are also delivered on site.

Front view


Garage side 


Dining Area  


Kitchen Area