Build Timeline

June 2013, Slab Pour
June 2013, Fenced and portaloo delivered
26th July 2013 Frames delivered. Termite matting down
28th July 2013 SS reporting that Blackheath brick is out of stock and Boral offerred another expensive brick.  :)
29th July 2013 Frames are up
30th July 2013 Confirmed SS to go ahead with new brick - Choc tan Velour.
2nd Aug 2013 Carpenters to continue with frames
5th/6th Aug 2013 Alfresco, Garage frames completed. Fixed Kitchen glass splashback, Laundry doors
7th Aug 2013  Bricks delivered
8th/9th Aug 2013 Brickies to start
8th Aug - No activity due to rain
9th Aug - Bricking
13th Aug - Second Progress Payment request (Frames)
19th Aug - Upper storey bricking
19th Aug - Plumbers on site
23rd Aug - Next set bricks delivered
27th Aug - Bricking completed
29th Aug - Third Progress Payment invoice received/ Roof Tiles delivered
1st Sep - Gutters and fascia installed
2nd Sep - ROOF !
9th Sep - Carpenters should be back on site
19th Sep - Half bricks are cleaned
21st Sep - Painters on site. Eaves, weatherboards, downpipes painted.
 23Sep - Roof tiles installed for garage and alfresco
25th Sep - Scaffolding down
27th Sep - Aircon rough ins
30th Sep, 1st Oct - Timber feature
2nd Oct - Rawson's certifier to inspect & our private inspector to inspect
3rd Oct - Electrical rough-ins to start
4th Oct - Insulation
7th Oct - Gyprocking
9th Oct - Brick clean on lower level
            - Gyprocking completed
            - Stairs gone in
11th Oct - Temporary Lockup
- Carpenters onsite for fixing cornices and doors.
 17th Oct - Wet area tiling begins
 26th Oct - Kitchen/ensuite/bathroom cabinets installed
12th Nov - Painting
15th Nov - Electricals
23rd Nov - next coat Painting
 29th Nov - Plumbing
2nd Dec - Electricians fix up few lights
3rd Dec - Insulation
4th Dec - Walkthrough with SS
                Tilers on site for main floor tiling and one bathroom
5th Dec - Carpenters on site - fixing architraves, door handles and locks