Thursday, September 26, 2013

Scaffolding down.. :)

Scaffolding is taken down this week. Roof tiles were installed for alfresco and garage. As per the SS, electrical rough ins also starts this week. Rawson' s inspectors are also scheduled for this week.

Our private inspector will be going to site next week

Brick cleaning, Painting

There was not much work in site last week.
Half of the bricks were cleaned and painters were in to paint the weather boards,  eaves and downpipes. Its looking good

Saturday, September 14, 2013

Eaves and Weatherboards are in

This week we had the carpenters come back on site to fix few windows. The roof rails are taken down. The eaves and weather boards are in. The cedar screens are fixed on one side. Brickies also should be back to fit window sils.

Next week is going to be a quiet one with the brick cleaners scheduled on Thursday and painters on Friday for painting weather boards. 

Sunday, September 8, 2013

ROOF

We have a roof (happy dance). Garage and alfresco roofs are yet to be laid.

Bricking complete, Gutter and fascia installed

Here are some pictures. So officially bricking is completed. Gutter and fascia has gone in.

Roof tiles are delivered on site.