Tuesday, February 25, 2014

30 Jan - handover date moved forward

I received a call from SS and he mentioned that the handover is a day earlier. So Thursday, Feb 6th it is!

Jan 24 - final payment processes

Once we received a handover date, we started the process for issuing the final payment.
We notified our banker at the earliest so that they could arrange an inspection/final evaluation for the property. Also gathered interim occupancy certificate from Rawson admin section.

Jan 24 - PCI

We were excited and at the same time nervous when we walked into the house for PCI.

We had prepared ourselves very well and we had a clear idea of the areas we need to concentrate in each rooms.

Also we prepared a list of external items which required rectification well in advance - mainly mortar repointing issues, cladding and glass damaged by vandals etc.. it made it really easier for us.

Altogether PCI went well and finally we had a date for handover - Feb 7th.

Jan 22 - Private inspection

We manged to get the private inspection done just before we went in for PCI.

I found that really helpful because we got enough time to go over the report and we could concentrate on other stuffs which requires rectification